Tuesday, June 29, 2021

Greenville Project Updates

The projects detailed below are large scale projects happening in addition to our regular, day to day, operations. Their completion may be managed by village staff or the services may be contracted with a third party. Please remember that all of the information, and time lines, are weather dependent and subject to change at any time.

A more detailed description, as well as photos and additional information, about our Capital Improvement Projects can be found on our website at: http://townofgreenville.com/projects.php.

Information about Outagamie County Highway Construction and Paving Projects can be found on their website at: https://bit.ly/3eGWRCJ

Information about WisDOT projects can be found on their website here:https://bit.ly/3fqFjKf

Please contact our Parks and Public Works office directly at (920)757-7276 with any questions.

Streets

  • Greenwood Road Reconstruction
    • Week of 6/28/21: Continue with the storm sewer installation between Rickey and Cedar Ln, continue cutting and stoning road, and possibly start a portion of the retention pond.
    • Week of 7/5/21: Installation of new utilities on Evening Star Dr, raising of house for pond, pond excavation, installation of water and sewer laterals north of Rickey Ln and continuation of road reconstruction.

Water & Sewer

  • STH 76 Force Main & Lift Station Improvements
    • Week of 6/28/21: Pavement was completed last week, and traffic is back to normal on STH 76. Thank you for your patience and keeping the job safe. Force main installation continues along STH 76 south of STH 15 near the shoulder, but traffic flow should be normal.
    • Week of 7/2/21: Force main installation completion is expected, and final testing will follow. Cleanup and
  • Annual Hydrant Flushing
    • This process will begin the week of June 7 and is scheduled to continue throughout the entire summer.

Parks, Recreation & Forestry

  • Schultz Farm Road
    • The construction of Schultz Farm Road, which provides access to the Sports Complex and Well #5, is scheduled for completion this summer. Utilities have been relocated and Vinton Construction will complete the project with construction of the right turn lane and paving the road surface north of Hwy 96.
  • Lions Park Street Lighting
    • WE Energies has completed installation of the new street lighting for Lions Park. Village staff will be working to remove the old light poles.
  • Jennerjohn Park Parking Lot Reconstruction
    • Staff is currently working with Cedar Corporation on the design and bidding for the reconstruction of the main Jennerjohn Park parking lot. The lot will be designed to be more efficient for parking and stormwater facilities will be installed to direct water to the pond. Construction is planned for September/October.
  • Lions Park Development
    • The Lions Club will be resuming work on the southeast corner of the park this summer with completion of the sport courts. The Lions Club have decided to change the planned tennis court area to a dedicated pickle ball facility. The facility will include 8 pickle ball courts. Additional facilities will include sand volleyball and basketball.
  • Community Park Redevelopment
    • The Village is working with Cedar Corporation this summer to continue planning and design work for the potential redevelopment of Community Park. This is a partnership project between the Village, Greenville Youth Sports and Greenville Civic Club.

Friday, June 25, 2021

The Parks, Recreation & Forestry Department's Feature Friday

Each Friday, The Parks, Recreation and Forestry Department features something new for residents and visitors to learn more about. This week, we want to tell you about a project we recently completed. Have you wondered about the work near the Highway 76 trail tunnel?

This work was to replace the existing 24” HDPE plastic culverts. These culverts were failing and heaving through the pavement causing a safety issue. This is a common issue with plastic culverts due to frost cycles. Two 24” concrete culverts were installed to help prevent future failures and the asphalt pavement was replaced to provide a smooth surface.

The tunnel under HWY 76 connects the trail system that runs along Municipal Drive from the Greenville Lions Park to Jennerjohn Park. This section of trail is often used to access the YMCA and Greenville Middle school.


To see more photos of today's Feature Friday or to see more posts like this, check out the Parks & Recreation Facebook page at https://www.facebook.com/greenvilleparkandrec

Friday, June 18, 2021

The Parks, Recreation & Forestry Department's Feature Friday

Each Friday, The Parks, Recreation and Forestry Department features something new for residents and visitors to learn more about. This week, we want to tell you about Elder Brook Park. Does anyone know what this park used to be named?
 
Formally known as Glen Valley Park, Elder Brook is an 8.5 acre park that features a walking trail, open play space, retention pond, and on street parking. The name was changed last year to reflect the school that once sat on that property. Parts of the school house foundation can still be seen in the wooded southeast corner of the park.
 
According to a report done by John Richards at UW-Milwaukee:
“The Elder Brook School site harbors the remains of the School District No. 3 Schoolhouse and is located in Greenville Township, Outagamie County, Wisconsin. The land on which the school was constructed was deeded as a school house property in 1854 but the earliest available plat maps of the township dates to 1873. This map depicts a school on the property. However, it is likely that the original construction occurred in 1854 or soon thereafter as free public education was mandated by Wisconsin’s state constitution six years earlier in 1848. By 1937 state-wide compliance with Wisconsin’s law resulted in the creation of 7,777 school districts with 6,181 one-room schools (Apps 1996:177). State mandated consolidation efforts reduced that number to 2,289 one-room schools in 1959 but as late 1964, 595 one-room schools remained in operation; 20 of these were located in Outagamie County (Rothwell 1963). Today, Wisconsin has 424 public school districts with 2,215 schools, none of which are operating one-room school houses. A standing structure on the Elder Brook school site is last visible on a 1943 aerial photo but is no longer present on a 1957 aerial photo of the site.”


To see more photos of today's Feature Friday or to see more posts like this, check out the Parks & Recreation Facebook page at https://www.facebook.com/greenvilleparkandrec

Wednesday, June 16, 2021

Greenville Project Updates

The projects detailed below are large scale projects happening in addition to our regular, day to day, operations. Their completion may be managed by village staff or the services may be contracted with a third party. Please remember that all of the information, and time lines, are weather dependent and subject to change at any time.

A more detailed description, as well as photos and additional information, about our Capital Improvement Projects can be found on our website at: http://townofgreenville.com/projects.php.

Information about Outagamie County Highway Construction and Paving Projects can be found on their website at: https://bit.ly/3eGWRCJ

Information about WisDOT projects can be found on their website here:https://bit.ly/3fqFjKf

Please contact our Parks and Public Works office directly at (920)757-7276 with any questions.

Streets
  • Greenwood Road Reconstruction
    • Week of 6/14/21: Continuing to cut and stone new roadway and driveway aprons between Cedar Ln and HWY 15 and installation of sanitary sewer laterals and water laterals to homes between Cedar Ln and Rickey Ln and
    • Week of 6/21/21: Continue with the same activities as above, and possibly start the installation of storm sewer between Cedar Ln and Rickey Ln.

Water & Sewer
  • STH 76 Force Main & Lift Station Improvements
    • Week of 6/14/21: STH 76 force main installation continues North of the railroad tracks and across Everglade Road to Lift Station 1. Concrete paving North of the STH 15/76 intersection continues. Everglade Road at times will require one way flagging at the intersection of STH 76. PLEASE BE CAREFUL AND SLOW DOWN. 
    • Week of 6/21/21: STH 76 force main installation nears completion, and the remaining asphalt paving begins.
  • Annual Hydrant Flushing
    • This process will begin the week of June 7 and is scheduled to continue throughout the entire summer.

Parks, Recreation & Forestry
  • Schultz Farm Road
    • The construction of Schultz Farm Road, which provides access to the Sports Complex and Well #5, is scheduled for completion this summer. Utilities have been relocated and Vinton Construction will complete the project with construction of the right turn lane and paving the road surface north of Hwy 96.
  • Lions Park Street Lighting
    • WE Energies has completed installation of the new street lighting for Lions Park. Village staff will be working to remove the old light poles.
  • Jennerjohn Park Parking Lot Reconstruction
    • Staff is currently working with Cedar Corporation on the design and bidding for the reconstruction of the main Jennerjohn Park parking lot. The lot will be designed to be more efficient for parking and stormwater facilities will be installed to direct water to the pond. Construction is planned for September/October.
  • Lions Park Development
    • The Lions Club will be resuming work on the southeast corner of the park this summer with completion of the sport courts. The Lions Club have decided to change the planned tennis court area to a dedicated pickle ball facility. The facility will include 8 pickle ball courts. Additional facilities will include sand volleyball and basketball.
  • Community Park Redevelopment
    • The Village is working with Cedar Corporation this summer to continue planning and design work for the potential redevelopment of Community Park. This is a partnership project between the Village, Greenville Youth Sports and Greenville Civic Club.
  • Lions Park Parking and Traffic Pattern Change
    • The Village recently added parking stalls and changed the traffic pattern at Lions Park in an effort to accommodate the demand for parking while also increasing safety for park users. The north entrance to the park is now an entrance only with one way traffic until the road that leads to the archery range. The south entrance remains two way traffic.

Friday, June 11, 2021

The Parks, Recreation & Forestry Department's Feature Friday

Each Friday, the Parks, Recreation and Forestry Department features something new for residents and visitors to learn more about. This week, we want to tell you about the playground at Jennerjohn Park.

The playground at Jennerjohn Park is the biggest, and probably most popular, park playground here in Greenville. There are three different playground areas to choose from. A sand area is located furthest north and is about 1,800 square feet in size. It includes two diggers – one for standing and one for sitting – and a metal fire truck for “driving” and climbing.

The sand area and fire truck are originals to play ground but, in 2005 a community build replaced one single playground with the two that are currently there. One of the playground areas is designed for children ages 2-5 and is approximately 3000 square feet in size. It includes equipment to slide, climb, ride, and swing. The other is designed for ages 5-12 and offers much of the same play opportunities but on a higher skill level. That area is approximately 5000 square feet in size.

Other activities to enjoy while playing at the park include a ball diamond, open play space, tennis courts, the Heritage Fountain and access to the trail system. The covered pavilion offers public restroom and when not rented, shade and picnic tables as well. You’ll even find activities here in the winter months when we have our sledding hill, ice rink and ski trial!


To see more photos of today's Feature Friday or to see more posts like this, check out the Parks & Recreation Facebook page at https://www.facebook.com/greenvilleparkandrec

Wednesday, June 9, 2021

Community Movie Night

We are only a week away from our first movie of the year!!

The movie will start at dusk but make sure you come early to see with the Greenville Fire Department and First Responders! They will be hanging out with us from 7:30-8:30pm.  See you there?



Find us on Facebook for more details!

Friday, June 4, 2021

The Parks, Recreation & Forestry Department's Feature Friday

Each Friday, the Parks, Recreation and Forestry Department features something new for residents and visitors to learn more about. This week, we want to share our Pebble Ridge Park with you!

Pebble Ridge Park may seem like just another small neighborhood park but with 13 acres, it has a lot to offer! The playground was designed for kids of all ages and has equipment to climb, slide, hang and swing. Next to the playground there is a picnic area and plenty of large open play space. A beautiful prairie overlooks the retention pond and on street parking allows for easy access to all areas of the park.

Walking trails run throughout the park and provide many different views. You can walk through a wooded area, part of the prairie and along the retention pond. In August of 2019, approximately 1,600 feet of 8 foot wide trail was paved to provide a cleaner, safer surface for users. Prior to paving, the trail was all gravel and frequently washed out, creating low spots. The paved segment branches off to align with both entrances of the woods on either side of the prairie. The wooded section of the trail remains gravel. The whole trail is approximately one half mile.


To see more photos of today's Feature Friday or to see more posts like this, check out the Parks & Recreation Facebook page at https://www.facebook.com/greenvilleparkandrec

Wednesday, June 2, 2021

Greenville Project Updates

The projects detailed below are large scale projects happening in addition to our regular, day to day, operations. Their completion may be managed by village staff or the services may be contracted with a third party. Please remember that all of the information, and time lines, are weather dependent and subject to change at any time.

A more detailed description, as well as photos and additional information, about our Capital Improvement Projects can be found on our website at: http://townofgreenville.com/projects.php.

Information about Outagamie County Highway Construction and Paving Projects can be found on their website at: https://bit.ly/3eGWRCJ 

Information about WisDOT projects can be found on their website here:https://bit.ly/3fqFjKf 

Please contact our Parks and Public Works office directly at (920)757-7276 with any questions.

Streets

  • Greenwood Road Reconstruction
    • Week of 5/31/21: Continue installation of water and sanitary sewer main north of Cedar Ln, continue to construct new roadway south of Cedar Ln, and continue with brushing and grubbing.
    • Week of 6/7/21: Continue with the same activities as above.

Water & Sewer

  • STH 76 Force Main & Lift Station Improvements
    • Week of 5/31/21: Auger Bore casing installation continues under STH 15 and under the STH 76 box culvert.
    • Week of 6/7/21: STH 76 Railroad crossing will be closed for Auger Bore casing installation and back open June 11, 2021. Traffic control will continue on STH 76 just south of and then north of the railroad tracks to Everglade Road.
  • Annual Hydrant Flushing
    • This process will begin the week of June 7 and is scheduled to continue throughout the entire summer.
  • Hydrant Painting
    • This process is scheduled to begin on June 3 will take approximately one month
    • During this process, the old paint will be removed via sand blasting leaving the hydrant white before they are repainted. These white hydrants are not cause for concern and are still operational. 

Parks, Recreation & Forestry

  • Schultz Farm Road
    • The construction of Schultz Farm Road, which provides access to the Sports Complex and Well #5, is scheduled for completion this summer. Work has resumed with the relocation of utilities. Following the utility work, Vinton Construction will complete the project with construction of the right turn lane and paving the road surface north of Hwy 96. 
  • Lions Park Street Lighting
    • WE Energies has completed installation of the new street lighting for Lions Park. Village staff will be working to remove the old lighting.
  • Jennerjohn Park Parking Lot Reconstruction
    • Staff is currently working with Cedar Corporation on the design for the reconstruction of the main Jennerjohn Park parking lot. The lot will be designed to be more efficient for parking and stormwater facilities will be installed to direct water to the pond. Construction is planned for September/October.
  • Lions Park Development
    • The Lions Club will be resuming work on the southeast corner of the park this summer with completion of the tennis courts, basketball courts and sand volleyball court. The tennis courts will also be striped to accommodate pickle ball.
  • Community Park Redevelopment
    • The Village will be working with Cedar Corporation this summer to continue planning and design work for the potential redevelopment of Community Park. This is a partnership project between the Village, Greenville Youth Sports and Greenville Civic Club.