Greenville Project Update


The projects detailed below are large scale projects happening in addition to our regular operations. Their completion may be scheduled to be done by town staff or the services may have been contracted with a third party. Please remember that all of the information and time lines are weather dependent and subject to change at any time.

A more detailed description and additional information about these projects can be found on our website at: http://townofgreenville.com/projects.php or by contacting our office at (920)757-7276.


Streets

  • Greenwood Road Urbanization (STH 15 - Parkview Dr)
    • An existing conditions survey has been performed and a conceptual design is being drafted.
    • The project is planned to be constructed in 2021.
  • South Creek Drive (School Rd-Molly Marie Ct)
    • Project Completed September 29, 2020
  • Spring Road Pulverize and Pave (North Rd-Julius Dr)
    • Project Completed July 17, 2020

Stormwater

  • Community Park Dredging
    • Dredging operations started on September 15, 2020 to restore drainage to the Park. Contractor began their work at the pedestrian trail stream crossing and on September 17, 2020 moved west of the trail. Work concluded and this project was finished on September 22, 2020. View before and after photos by clicking here.
  • STH 15 East/West Basins
    • Project Completed September 24, 2020

Water & Sewer

  • STH 15 Utility Relocates
    • Work began the week of September 28, 2020
    • Utility relocates along STH 15 between Julius Drive and Lily of the Valley Drive. 
    • Existing sanitary sewer and water main facilities are being relocated to accommodate the future STH 15 WisDOT expansion project.
  • Industrial Park Water Valves
    • Replaced leaking water valves in the the Greenville Industrial Park. Work was completed by Jossart Brothers, Inc. the week of September 21, 2020 
  • Cross Connections
    • The Purpose of the Town of Greenville’s Cross Connection Control Program, as defined in the local Ordinance §340-26, is to help eliminate possible contamination of the public water distribution system.
    • These inspections began in February 2020 but were suspended shortly after due to the novel coronavirus (COVID-19) pandemic. The Sanitary District was hoping to complete these inspections at the end of summer, but have since decided to suspend the program again. 

Parks, Recreation & Forestry

  • Greenville Sports Complex
    • Rettler Corporation has been contracted to design and engineer a new entrance road to the property. This new entrance road is consistent with the Master Plan for the park and will provide a safer access to the park from Hwy 96. This entrance road will be an official Town road and will also provide safe access to Well #5 and a private residence. Construction is expected to begin in fall 2020 with completion in Spring 2021.
  • Lions Park
    • The Lions Club is installing the fencing for the future sport courts in the southeast quadrant of the park as well as completing landscape restoration of the area. Any additional work in this area is postponed due to the cancellation of their main fundraising efforts for 2020.
    • Town staff is installing a concrete pad and fenced enclosure for the trash and recycling dumpsters near the Barn Pavilion.
  • Community Park
    • Dredging of the creek behind the ball fields is complete.