The projects detailed below are large scale projects happening in addition to our regular, day to day, operations. Their completion may be managed by village staff or the services may be contracted with a third party. Please remember that all of the information and time lines are weather dependent and subject to change at any time.
A more detailed description, as well as photos and additional information, about our Capital Improvement Projects can be found on our website at: http://townofgreenville.com/projects.php.
Information about Outagamie County Highway Construction and Paving Projects can be found on their website at: https://bit.ly/3eGWRCJ
Information about WisDOT projects can be found on their website here:https://bit.ly/3fqFjKf
Please contact our Parks and Public Works office directly at (920)757-7276 with any questions.
Streets
- Greenwood Road Reconstruction
- Week of 7/26/21: Finish cutting and stoning the road and sidewalk between the intersections of Cedar and Rickey Ln, intersection of Cedar to be done after natural gas is replaced. Possibly start replacing utilizes north of Rickey Ln.
- Week of 8/2/21: Possible excavation of pond, cutting and stoning of road south to Hwy 15 and possibly start replacing utilities north of Rickey Ln
Water & Sewer
- STH 76 Force Main & Lift Station Improvements
- Week of 7/26/2021: Lift Station 2 is partially completed and manholes 2, 3, 4 will be installed next week. The force main is completed to both lift stations. Landscaping is complete with a few items to touch up along the STH 76, and we appreciate your patience. There will still be some minor work near and along the highway to complete the restoration.
- Week of 8/2/2021: Lift Station 2 manholes, valve vault and piping.
- Annual Hydrant Flushing
- This process began the week of June 7 and is scheduled to continue throughout the rest of the summer.
Parks, Recreation & Forestry
- Schultz Farm Road
- The construction of Schultz Farm Road, which provides access to the Sports Complex and Well #5, is scheduled for completion this summer. Utilities have been relocated and Vinton Construction will complete the project with construction of the right turn lane and paving the road surface north of Hwy 96.
- Jennerjohn Park Parking Lot Reconstruction
- Staff is currently working with Cedar Corporation on the design and bidding for the reconstruction of the main Jennerjohn Park parking lot. The lot will be designed to be more efficient for parking and stormwater facilities will be installed to direct water to the pond. Construction is planned for September/October.
- Lions Park Development
- The Lions Club will be resuming work on the southeast corner of the park this summer with completion of the sport courts. The Lions Club have decided to change the planned tennis court area to a dedicated pickle ball facility. The facility will include 8 pickle ball courts. Additional facilities will include sand volleyball and basketball.
- Community Park Redevelopment
- The Village is working with Cedar Corporation this summer to continue planning and design work for the potential redevelopment of Community Park. This is a partnership project between the Village, Greenville Youth Sports and Greenville Civic Club.