The projects detailed below are large scale projects happening in addition to our regular operations. Their completion may be scheduled to be done by town staff or the services may have been contracted with a third party. Please remember that all of the information and time lines are weather dependent and subject to change at any time.
A more detailed description and additional information about these projects can be found on our website at: http://townofgreenville.com/projects.php or by contacting our office at (920)757-7276.
Streets
- Greenwood Road Urbanization (STH 15 - Parkview Dr)
- An existing conditions survey has been performed and a conceptual design is being drafted.
- The project is planned to be constructed in 2021.
- South Creek Drive (School Rd-Molly Marie Ct)
- Project Completed September 29, 2020 - See photos here
- Spring Road Pulverize and Pave (North Rd-Julius Dr)
- Project Completed July 17, 2020 - See photos here
Stormwater
- Community Park Dredging
- Project Completed September 22, 2020. - See photos here
- STH 15 East/West Basins
- Project Completed September 24, 2020 - See photos here
- Ditching Maintenance
- Everglade Road: south side of the roadway, from just east of the post office 350 linear feet to a private driveway. This maintenance will remove the sediment that currently fills the ditch causing water and sediment to enter onto the roadway surface during rain events. It will also help to prevent winter ice issues from forming on the road.
- Lily of the Valley/Maple Terrace/Buttercup Court: approximately 1900 linear feet of ditches will be maintained. This maintenance will remove 6-12 inches of sediment and vegetation from the bottom of the ditch. This prevents adequate stormwater conveyance during storm events.
Water & Sewer
- STH 15 Utility Relocates
- Work began the week of September 28, 2020
- Utility relocates along STH 15 between Julius Drive and Lily of the Valley Drive.
- Existing sanitary sewer and water main facilities are being relocated to accommodate the future STH 15 WisDOT expansion project.
Parks, Recreation & Forestry
- Greenville Sports Complex
- Rettler Corporation has been contracted to design and engineer a new entrance road to the property. This new entrance road is consistent with the Master Plan for the park and will provide a safer access to the park from Hwy 96. This entrance road will be an official Town road and will also provide safe access to Well #5 and a private residence. Construction is expected to begin in fall 2020 with completion in Spring 2021.
- Lions Park
- The Lions Club is installing the fencing for the future sport courts in the southeast quadrant of the park as well as completing landscape restoration of the area. Any additional work in this area is postponed due to the cancellation of their main fundraising efforts for 2020.
- Town staff is installing a concrete pad and fenced enclosure for the trash and recycling dumpsters near the Barn Pavilion.