Tuesday, September 22, 2020

Greenville Project Update

The projects detailed below are large scale projects happening in addition to our regular operations. Their completion may be scheduled to be done by town staff or the services may have been contracted with a third party. Please remember that all of the information and time lines are weather dependent and subject to change at any time.

A more detailed description and additional information about these projects can be found on our website at: http://townofgreenville.com/projects.php or by contacting our office at (920)757-7276.

Streets
  • Greenwood Road Urbanization (STH 15 - Parkview Dr)
    • An existing conditions survey is currently being performed. Following this, a conceptual design will be drafted.
    • The project is planned to be constructed in 2021.
  • South Creek Drive (School Rd-Molly Marie Ct)
    • Week of 9/21/20: Finish all restoration on project, and monitor project restoration for grass growth and erosion.
    • Week of 9/28/20: Monitor project restoration for grass growth and erosion.
  • Spring Road Pulverize and Pave (North Rd-Julius Dr)
    • Week of 9/21/20: Monitor project restoration for grass growth and erosion.
    • Week of 9/28/20: Monitor project restoration for grass growth and erosion.
Stormwater
  • Community Park Dredging
    • September 15/16, 2020: Contractors completed the dredging operations and final restoration to the pedestrian trail stream crossing.
    • September 17, 2020: Dredging operations resumed west of the trail
    • The completion of this project will increase the capacity of the waterway and improve overall site drainage.
  • STH 15 East/West Basins
    • Anticipated to begin in August 2020
    • The STH 15 east basin will be constructed as a dry detention basin to serve as a flood control facility.
    • The STH 15 west basin will be constructed as a wet detention basin to increase the capacity of the existing flood control facility as well as provide stormwater quality control.
    • The completion of this project will reduce flooding events of nearby residential properties that have been historically affected.
Water & Sewer
  • STH 15 Utility Relocates
    • Anticipated to begin the week of September 28
    • Utility relocates along STH 15 between Julius Drive and Lily of the Valley Drive. Existing sanitary sewer and water main facilities will be relocated to accommodate the future STH 15 WisDOT expansion project.
  • Cross Connections
    • The Purpose of the Town of Greenville’s Cross Connection Control Program, as defined in the local Ordinance §340-26, is to help eliminate possible contamination of the public water distribution system.
    • These inspections began in February 2020 but were suspended shortly after due to the novel coronavirus (COVID-19) pandemic. The Sanitary District is now hoping to complete the remaining inspections.
Parks, Recreation & Forestry
  • Greenville Sports Complex
    • Rettler Corporation has been contracted to design and engineer a new entrance road to the property. This new entrance road is consistent with the Master Plan for the park and will provide a safer access to the park from Hwy 96. This entrance road will be an official Town road and will also provide safe access to Well #5 and a private residence. Bidding for the project is underway and construction is expected to be complete in fall 2020.
  • Lions Park
    • The Lions Club is installing the fencing for the future sport courts in the southeast quadrant of the park as well as completing landscape restoration of the area. Any additional work in this area is postponed due to the cancellation of their main fundraising efforts for 2020.
    • Town staff is installing a concrete pad and fenced enclosure for the trash and recycling dumpsters near the Barn Pavilion.
  • Community Park
    • Dredging of the creek behind the ball fields is in progress.