The projects detailed below are large scale projects happening in addition to our regular operations. Their completion may be scheduled to be done by town staff or the services may have been contracted with a third party. Please remember that all of the information and time lines are weather dependent and subject to change at any time.

A more detailed descriptions, additional information or photos of completed projects, visit our website at: http://townofgreenville.com/projects.php or contact our Public Works office at (920)757-7276.

Streets

  • Greenwood Road Urbanization (STH 15 - Parkview Dr)
    • An existing conditions survey has been performed and a conceptual design is being drafted.
    • The project is planned to be constructed in 2021

Stormwater

  • Ditching Maintenance
    • Everglade Road: south side of the roadway, from just east of the post office 350 linear feet to a private driveway. This maintenance will remove the sediment that currently fills the ditch causing water and sediment to enter onto the roadway surface during rain events. It will also help to prevent winter ice issues from forming on the road.
    • Lily of the Valley/Maple Terrace/Buttercup Court: approximately 1900 linear feet of ditches will be maintained. This maintenance will remove 6-12 inches of sediment and vegetation from the bottom of the ditch. This prevents adequate stormwater conveyance during storm events.


Water & Sewer

  • STH 15 Utility Relocates
    • Work began the week of September 28, 2020
    • Utility relocates along STH 15 between Julius Drive and Lily of the Valley Drive.
    • Dorner is currently installing water main and will be replacing all of the water services in the project after they get the main installed.
  • Manhole Maintenance
    • Work scheduled to begin week of November 9
    • Visu-Sewer, Inc has been contracted to refurbish manholes needing maintenance due to H2S gases. 

Parks, Recreation & Forestry

  • Greenville Sports Complex
    • Construction of Schultz Farm Road is underway and will be completed in two phases, with phase two being completed in spring. Schultz Farm Road is the new entrance to the Greenville Sports Complex. It is an official Town road and will also serve as access to Well #5 and a private residence. This new road will provide a safer access to the park and includes a right turn lane and bypass lane on Hwy 96.