Wednesday, July 15, 2020

Greenville Project Update

The projects detailed below are large scale projects happening in addition to our regular operations. Their completion may be scheduled to be done by town staff or the services may have been contracted with a third party. Please remember that all of the information and time lines are weather dependent and subject to change at any time.

A more detailed description and additional information about these projects can be found on our website at: http://townofgreenville.com/projects.php or by contacting our office at (920)757-7276.


Streets

  • Greenwood Road Urbanization (STH 15 - Parkview Dr)
    • An existing conditions survey is currently being performed. Following this, a conceptual design will be drafted.
    • The project is planned to be constructed in 2021.
  • South Creek Drive (School Rd-Molly Marie Ct)
    • Week of 7/13/20: Installation of culverts and endwalls 
    • Week of 7/20/20: Continue culvert installation along with common excavation of roadway and ditching
  • Spring Road Pulverize and Pave (North Rd-Julius Dr)
    • Week of 7/13/20: Finish restoration along roadway and ditches. 
    • Week of 7/20/20: Finish restoration along roadway and ditches, as needed.

Stormwater

  • Community Park Dredging
    • Anticipated to begin in September 2020
    • Dredging of the waterway along the south boundary of Community Park to remove sediment and undergrowth. 
    • The completion of this project will increase the capacity of the waterway and improve overall site drainage.
  • STH 15 East/West Basins
    • Anticipated to begin in August 2020
    • The STH 15 east basin will be constructed as a dry detention basin to serve as a flood control facility. 
    •  The STH 15 west basin will be constructed as a wet detention basin to increase the capacity of the existing flood control facility as well as provide stormwater quality control. 
    •  The completion of this project will reduce flooding events of nearby residential properties that have been historically affected.

Water & Sewer

  • Annual Hydrant Exercising and Flushing
    • Began the week May 11 and is still in progress.
    • It is normal to notice a slight discoloration or cloudiness to your water while staff is working on the hydrants in your area. To help clear up the color, you can run the cold water tap located closest to your water meter until the water runs clear.
  • STH 15 Utility Relocates 
    • Anticipated to begin in August 2020
    • Utility relocates along STH 15 between Julius Drive and Lily of the Valley Drive. Existing sanitary sewer and water main facilities will be relocated to accommodate the future STH 15 WisDOT expansion project.

Parks, Recreation & Forestry

  • Greenville Sports and Splash Park
    • Rettler Corporation has been contracted to design and engineer a new entrance road to the property. This new entrance road is consistent with the Master Plan for the park and will provide a safer access to the park from Hwy 96. Construction is planned to be completed in 2020.
    • The Field of Dreams Referendum Steering Committee brought a formal recommendation to the Town Board on May 18, 2020 to hold an advisory referendum with the August 11, 2020 election regarding the development of Phase 1 of the Field of Dreams Property, now dubbed the Greenville Sports and Splash Park. The Town Board approved the resolution to hold the advisory referendum. Up to date information regarding this project can be found at this website: http://www.townofgreenville.com/SportsandSplashPark/index.php