Greenville Project Update

The projects detailed below are large scale projects happening in addition to our regular operations. Their completion may be scheduled to be done by town staff or the services may have been contracted with a third party. Please remember that all of the information and time lines are weather dependent and subject to change at any time.

A more detailed description and additional information about these projects can be found on our website at: http://townofgreenville.com/projects.php or by contacting our office at (920)757-7276.

Streets
  • Greenwood Road Urbanization (STH 15 - Parkview Dr)
    • An existing conditions survey is currently being performed. Following this, a conceptual design will be drafted. 
    • The project is planned to be constructed in 2021.  
  • South Creek Drive (School Rd-Molly Marie Ct) 
    • New tentative start date is scheduled for the week of July 6 
  • Spring Road Pulverize and Pave (North Rd-Julius Dr) 
    • Week of 6/15/20: Fine grading the roadway, preparing it for asphalt.
    • Week of 6/22/20: Asphalting and shouldering the roadway.

Stormwater
  • The Greenridge Terrace Subdivision Stormwater Pond Dredging project is starting the week of June 15th. The subdivision is located south of Community Park and West of STH 76. One of the existing Stormwater treatment ponds is in need of sediment removal to comply with Wisconsin Department of Natural Resources water pollution reduction goals to keep sediment and phosphorous out of State Waterways from developed areas. The project is expected to take 3-4 days to complete. You may see dump trucks coming onto STH 76 from Greenridge Drive that will transport dredging spoils to a disposal site.

Water & Sewer 
  • Hydrant Exercising and Flushing began the week May 11 and is still in progress.  It is normal to notice a slight discoloration or cloudiness to your water while staff is working on the hydrants in your area. To help clear up the color, you can run the cold water tap located closest to your water meter until the water runs clear.

Parks, Recreation & Forestry
  • Greenville Sports and Splash Park
    • Rettler Corporation has been contracted to design and engineer a new entrance road to the property. This new entrance road is consistent with the Master Plan for the park and will provide a safer access to the park from Hwy 96. Construction is planned to be completed in 2020. 
    • The Field of Dreams Referendum Steering Committee brought a formal recommendation to the Town Board on May 18, 2020 to hold an advisory referendum with the August 11, 2020 election regarding the development of Phase 1 of the Field of Dreams Property, now dubbed the Greenville Sports and Splash Park. The Town Board approved the resolution to hold the advisory referendum. Up to date information regarding this project can be found at this website: http://www.townofgreenville.com/SportsandSplashPark/index.php
  • Street Tree Planting 
    • Town staff is currently working on installing irrigation bags on all newly planted street trees. Please continue water trees as usual until the irrigation bag is installed. Once installed, the irrigation bag can be filled once per week to keep the tree adequately watered.