Streets
- Greenwood Road Urbanization (STH 15 - Parkview Dr)
- An existing conditions survey is currently being performed. Following this, a conceptual design will be drafted.
- The project is planned to be constructed in 2021.
- South Creek Drive (School Rd-Molly Marie Ct)
- Construction is scheduled to begin the week of June 8
- Spring Road Pulverize and Pave (North Rd-Julius Dr)
- Week of 6/1/20: Continue with common road excavation and begin culvert installation and ditch cleaning.
- Week of 6/8/20: Continue with culvert installation and ditch cleaning. Begin concrete curb and gutter installation and fine grading the roadway.
Water & Sewer
- Hydrant Exercising and Flushing began the week May 11 and will continue throughout the next few months.
Parks, Recreation & Forestry
- Greenville Sports Complex
- Rettler Corporation has been contracted to design and engineer a new entrance road to the property. This new entrance road is consistent with the Master Plan for the park and will provide a safer access to the park from Hwy 96. Construction is planned to be completed in 2020.
- The Field of Dreams Referendum Steering Committee brought a formal recommendation to the Town Board on May 18, 2020 to hold an advisory referendum with the August election regarding the development of Phase 1 of the Field of Dreams Property. The Town Board approved the resolution to hold the advisory referendum.
- Street tree planting
- Street tree planting was completed by Srb’s Trees the week of May 11, 2020. Town staff will be installing the irrigation bags within the next couple of weeks.